Building a Log Home in Maine:
A Construction Journal

BASICS

The House Plans
Room Views
Home Page


CONSTRUCTION
ENTRIES AND
ARCHIVES

January 2008
December 2007
October 2007
September 2007
August 2007
July 2007
June 2007
May 2007
April 2007
March 2007
February 2007
January 2007
December 2006
November 2006
October 2006
September 2006
August 2006
July 2006
June 2006
May 2006
April 2006
March 2006
February 2006
Header Photo Archives

 

~ The bLog Home ~

Click here to read entries from June 16 to June 30.

THURSDAY, JUNE 15, 2006


What a difference a day makes!  We made up for lost time yesterday by managing to put up the next 16' section of ridge and all 17 rafters thereunto attached.  And we were even done by 4!  Things just fell into place nicely.

We began, reluctantly, with addressing the next piece of ridge.  Neither of us looked forward to getting the large timber up in the air, and the skyhooks we had ordered never showed up.  This forced us, of course, to hoist the beam up by hand, much the way we did with the first section.


Getting a post to support the far (right) side of the second ridge section was a bit more involved.    Since the break in the ridge fell directly above the second ceiling tie in the main room, I installed a post made from 2-2x6s beneath the tie and directly over the center carrying beam, while Bob built a similar post to go between the top of the beam and the bottom of the to-be-installed ridge section.  With that out of the way, we hoisted the ridge up by carrying first one end, then the other, up to the tops of two stepladders, then carrying each end respectively up to the staging above.  Then, with Bob on one section of staging and I on the other, we hoisted the beam the rest of the way (a few feet) and into place.  Fun stuff, this.

Photos note:  my camera is going wacko, so many of these photos have a unique look.  I decided to go ahead and post them since they actually look sort of cool, and almost as if they were relics from the pioneer days (if you try really hard...).  Later, you're sure to see better photos of these areas.


Next we cut an opposing pair of rafters for the far end of the ridge, and installed them in a similar way to those we did on previous days.  Despite initial worries about the difficulty of this, we found a method that worked well--pure manual labor, really--and got the two pieces installed, steadying the ridge.  T hen, we installed a similar pair in the center of the ridge before blitzing the remaining 7 backside (shed dormer) rafters before lunch.  Those were the easy ones, as they were only about 17' long. Again, we let the tails hang out overlong for later trimming.

After lunch, we continued by cutting and fitting the steeper rafters on the front of the house.  For each one, we cut the necessary cuts on the ground, then raised it to the second floor by lifting one end up from below and placing the end on the staging outside the house, then lifting that end to the second floor, then pushing the beam up from the ground, with one of us upstairs pulling.  Once half the beam was past the edge, it became balanced from the top and could easily be pulled in over the deck to safety.

    


Then, we raised the ridge end up using a similar method, and with Bob up top and me on the staging outside the house, we walked each rafter down to its final location for installation.  Since most of these rafters in the front now fell directly on a solid log wall, I used Sikaflex beneath these rafters at the outside wall; the ones on the second floor deck and on framed walls did not need the sealant.  We cut the tails of the rafters on the front at a line level with the 13th course of logs, since this is where the ceiling joists for the front porch would later be installed.  Since our front porch will have an enclosed--rather than open--ceiling, the rafter tails would not be exposed here.

By the end of the day, all the rafters were installed, and we looked forward to working on the gable dormer rafters in the morning.  I let it be known that my goal was to have the house roofed by July, which Bob thought was reasonable.  Now let's hope the current good weather holds...that would make all the difference.

WEDNESDAY, JUNE 14, 2006


Oh good:  more rain!  I was starting to shrivel up, after having no rain all day Tuesday.  Fortunately for my hydration needs--and those of the house and land--the day started off with a bang (literally), as we received a thunderstorm and some heavy rain at about 0630.   What was interesting about this was the fact that, according to the weather radar, the storm seemed to form virtually directly overhead; the radar was clear mere minutes before, but watching the loop later showed the storm forming instantaneously.  Later events would show that this was a trend for the entire day; we seemed to be stuck in an unstable air mass boundary that set this line of rain and storms passing right through our area for much of the day.  Good gravy!

(This image shows the line of rain and thunderstorms as of about 1500; if set in motion, you'd see how everything moved northeastward along this very line.

Kidding aside, the rain ended by about 0700 and didn't impact the beginning of our workday.  Bob was a bit late this morning, so I swept the water out of the house--again--while I waited, and then we got to work cutting and installing 5 additional rafters in the back of the house, on the shed dormer.  This completed the back rafters on the first section of ridge.
After a brief conference, we decided to continue installing the ridge rather than move staging and start installing the rafters for the front gable dormer, which had been our other thought.  But it seemed more efficient to leave the staging where it was upstairs and use it to work towards a yet-to-be-erected set of staging that we'd put up from the first floor below.
First, though, we installed the next cross tie between the loft deck and the front wall of the house, so that it would be all set before we needed to install rafters over it.  This tie, a 4"x8" beam about 18' long, was exceedingly heavy thanks to the pitch content in the wood, but we got it installed without issue; this was becoming old hat, after all.
With that done, we began to set up the staging in the living room.  We set up three 5' lifts of pipe staging, but found that the height wasn't quite high enough to make working easy on the ridge above.  We needed a couple feet, so Bob left to go retrieve his 2' set of pipe staging, which was at his son's house a few towns over.  It also happened to be lunchtime, so that was no bother.  The sky looked slightly threatening, so, thinking we might have a brief sprinkle or shower, we brought most of the tools down under the second floor for some basic protection.  I went down for lunch.
It began to rain, sure enough, but it was a lot harder than a pleasant sprinkle; it turned quickly into a downpour, so I put on a slicker and drove my truck up to the house to save the electric tools that were still outdoors, putting them all under a tarp on the bench.  When Bob returned a little later, the rain seemed to have retreated, and we got the 2' section of staging erected on top of the other three sections. 

Soon, though, it began to rain again, and we retreated to Bob's truck to wait it out--or so we thought.  Unfortunately, the rain never really stopped; it would peter out briefly, but before long would begin again at one intensity or another, all of which were too heavy in which to work.  We hung out for a couple hours, waiting and hoping, but by 1500 it was clear that we were beaten once again, so Bob went home and I put the tools away and came down myself. 

OK, Mother Nature:  you win!  You are all-powerful and omniscient, and I sincerely regret my bold statements of a few days ago where I opined--albeit jokingly--that I might, just might, have some control over your whims.  I stand most humbly corrected, and beg your forgiveness for my near-unforgivable transgression. By way of penance, I do hereby offer myself, knave-like, as a dedicated lifetime "weather crier", in which capacity I shall make it known to all who will listen--and some who won't--just how powerful  you indeed are, and that no man, ever, should begin to be so naive as to think that he--nay the entire human race, for that matter--has anything more than the most subtle of effects on your wiley ways.  You are the queen of all that is important, and I acquiesce.

TUESDAY, JUNE 13, 2006


Before we could continue, we needed to set up some staging.  Over the period of a couple hours in the morning, we set up staging inside and outside the house:  some pipe staging on the second floor, to allow us to reach the ridge pole and rafter tops, and some site-built wooden staging around the outside of the front and back walls on the cathedral end (south) of the house, made up from dimensional lumber nailed inside the window and door openings (where the nail holes wouldn't show later) with vertical supports and bracing as needed.

With the staging set up and ready for use, it was time to consider the installation of the first section of ridge pole--a 14' piece of 4" x 12" pine.  There was no way to get it up there without simply just getting it up there, so we horsed it into the building and then cantilevered it onto the second floor, where Bob cut it to the proper length to allow for the 12" overhang outside the gable, and to have the ridge break exactly at a rafter location. 

Now, we had to get it an additional 13' in the air, up to its final location.  The beam was heavy, and initially it seemed like a nearly insurmountable problem, but we came up with a plan to tip the beam up on end  and then lift and cantilever it over the 10' pipe staging.  In this manner, it was surprisingly easy to lift the beam up to the level of the staging.  From there, we got the gable end supported on its pocket, and then lifted the other end onto a previously-built A-frame (similar to those used to support the first floor during initial construction), before finally sliding the beam into the pocket and out through the gable the proper amount.

Flush with success, we climbed down for lunch, but then I noticed that we had installed the ridge upside down; we had chosen the better side to face down, and had marked the top accordingly.  However, to prevent damage to the bottom, exposed side, we had slid the beam up onto the staging on its top.  Once there, we had of course forgotten to flip the beam over before installing it.  Fortunately, it was a relatively easy fix, and after lunch we flipped the beam and reinstalled it.


Next, it was time to address the rafters; with the rafters measuring 4"x8" and up to 22' long, neither of us had been looking forward to this task.  The longest rafters proved to be quite heavy, but we managed to get one from its pallet out front, up the stairs and onto the second floor for cutting.  We also brought up an 18-footer for the opposing rafter, which would lay across the shed dormer and was therefore shorter.

Bob cut the rafters and bird's mouths to shape, and we prepared to install the two pieces.  For now, we left the rafter tails long, so that after all the rafters were installed we could snap a line and cut them all off evenly for best appearance.

Even though it was fewer than 24 hours ago as of this writing, I honestly can't remember if we installed the back rafter or the front rafter first.  I think we started with the back (shorter) rafter, and this proved to be easier than anticipated.  We lifted one end up on the back wall and slid it out a ways until it cleared the staging.  Then, we lifted the other end onto the staging and eventually lifted it to the ridge, where Bob secured it with some toenails.


We moved onto the front rafter, which extended right next to the front gable dormer and would form the first part of the cheek wall.  The seat cut at the bird's mouth sat right on the second floor, which helped hold the rafter in place while we lifted the top end onto the staging and, eventually, to the ridge.  Once both rafters were tacked at the ridge, we installed some 12" log screws to permanently secure them, and then permanently secured the two rafter tails.

For the next pair of rafters--this one located on the other side of the front gable dormer--we changed tactics a bit, and cut the long rafter right down on its pile before lifting it onto the second floor from the front of the house, saving the extra effort of maneuvering the unwieldy timber through the maze of braces and staging on the smallish second floor.  This worked surprisingly well, and, coupled with our knowledge and success gained from the first installations, we soon had the second pair of rafters installed.

    


The section of ridge and rafters began to truly define the roofline and the overall look of the house.  With the size and heft of the timbers, daily progress would be slow in comparison to traditional framed roof systems, but with continued good weather it seemed as if we could keep making good progress each day.

    


MONDAY, JUNE 12, 2006


We had more good weather today, though there was more rain overnight that had me concerned once again--and enough rain to get the whole house wet again, and leave large puddles on the floor that I had carefully swept dry yesterday.  Sigh.

We jumped right into things, and set to framing up the back of the shed dormer in the usual way.  By late morning, we had the wall stood up, secured, and braced. 

    


After lunch, we got to work on the gable end for the front gable dormer in the bedroom, and spent the afternoon laying out and framing this deceptively small wall.  The wall contains a large window, and we spent the bulk of the time figuring out at exactly what height the window should be located.  The plans for the house didn't give a lot of specific guidance in this area, but eventually we extrapolated the information we needed from several of the elevations of the house in the plans, and chose a height that would, when complete, approximate closely that shown on the front elevation. 

The height of the bottom of the window was important, since the porch roof would eventually come in just beneath the finished window, so we had to ensure that the window was located high enough to avoid that.  Once we figured that out, the remaining layout fell into place easily, and we completed the frame on the wall.  This was surprisingly time consuming thanks to the number of cuts required; plus, we had to install two of the 4x8 pine rafters in the wall, each of which requires several cuts for the bird's mouth where it crosses the plate.  We stood up this wall, secured and braced it, and that was pretty much it for the day.

    


SUNDAY, JUNE 11, 2006


I've been trying, through these past rainy weeks, to keep my sense of humor and perspective, and to just accept the fact that I cannot change the weather.  The delays in construction, while frustrating, can be dealt with.  But I was about ready to lose it this morning!

The house hasn't had a chance to truly dry out for weeks.  The constant barrage of rain and dampness, with hardly any sunshine at all even when it's not raining, is taking its toll, and the logs are discoloring and beginning to mildew.    This is discouraging, and is forcing me over the edge, mood-wise.  I know that the staining will clean up with TSP and bleach, oxalic acid, and sanding, but the need to do this simply creates more work down the road--and I worry that if the weather doesn't improve drastically soon, I may be unable to get all the staining out of what began as very clean and fresh logs.  The increase in staining and mildew in just the past few days is exponential.

    


Certainly this isn't the first time a log house under construction has been rained on, but we have had a pretty extraordinarily bad stretch of weather since we began construction back in May.  As if last week's heavy rain on 3 days wasn't enough, on top of the heavy rains of the week before and the week before that, we got even more rain--in the form of a couple hours of very heavy precipitation that just sort of rotated through our area out of nowhere--early this morning, further compounding the misery and wetness.  Poor Heidi had to endure listing to me rant on for several minutes; while it's pointless to complain about unchangeable things, sometimes one just has to vent a bit!

Fortunately for my mood, the weather actually improved today, late in the morning; the sky cleared (partly), and the sun came out, bringing a much-needed boost to morale.  It's funny:  this is the second time in recent memory that I have railed against the weather and shaken my proverbial fist to the skies in frustration, only to have the conditions drastically improve shortly thereafter.  Last summer, coming home from our cruise, I had a similar "discussion" with the weather Gods about some stubborn fog that we were stuck in; imagine my surprise when, mere minutes later, the fog lifted completely.  With today's events, I was starting to think that perhaps--just perhaps--I had some influence over the weather.  Hmmm...

I worked on several unrelated outdoor projects, and late in the day, Heidi told me that she was ready for me to knock over the remains of the Love Shack in the courtyard, which she had been systematically dismantling over the previous few weeks.  I was happy to oblige, and spent an hour or so knocking the roof down and then splintering the debris as much as possible with my tractor.  The ground was soft and muddy from the rain so I couldn't push things around as much as I needed to without getting hopelessly stuck, but what better way to end a day?

    


SATURDAY, JUNE 10, 2006


With rain showers of varying intensity this morning--yet again--I forced myself to go up to the house and finish installing the joist hangers in the basement.  Other than an occasional drip through one of the Advantech seams over my head, I stayed dry, and wrapped up the task in a couple hours.  It was hardly a satisfying or noteworthy task, but nonetheless was one more thing to check off the list.

FRIDAY, JUNE 9, 2006


The weather today was quite acceptable, actually, but unfortunately we had a "planned no-work day" since Bob had to finish the plumbing at his son Will's house.  It was just too bad that this happened to fall on one of the only decent days of the week, but what can you do.

To compensate, I started work on the tedious chore of installing joist hangers in the basement, to support the first floor joists.  During initial deck construction, we had just toenailed each joist to the center beam; now, it was time to consider getting these hangers installed--exciting stuff.  But progress is progress, after all. 

I worked on the hangers in the sopping wet, dark, dank basement for about an hour, getting about 1/3 of them installed (each hanger requires 12 nails, so it takes a while), before I decided that the weather outside was nice enough to do some outdoor tractor work, so I quit at that point and enjoyed the relatively good weather for a change.


THURSDAY, JUNE 8, 2006


Rain.  All day.  Heavy.

WEDNESDAY, JUNE 7, 2006


Well, the weather was once again uncooperative, but that didn't stop us from getting the north gable wall stood up and secured in place.  With the forecast calling for rain, and the leading edge of the precipitation at the Maine border first thing t his morning, we knew we were on borrowed time, and at least we managed to get the wall up--and just in time, because as we finished up, the rain began spitting.  (What a bore this is becoming, this rain.)

Before beginning, there were a few preparatory details to be dealt with.  First, Bob installed a couple pieces of scrap metal banding material (from the material deliveries) to the bottom plate of the wall, nailing them inside to the second floor.  He had to remove a piece of the sheathing on one side for sufficient access, as he had forgotten to put this banding in place before.  The banding would hold the base of the wall in place during lifting, not only properly aligning the wall, but also preventing it from slipping over the side and catastrophically to the ground--a hinge, basically.

While he did that, I installed some pine cleats to the top of the log walls to make the portion outside the log tongue even with the 2nd floor decking inside.  The manual had recommended cutting off the tongue on the 14th log course, but this seemed like unnecessary work; instead, I milled some scrap pine into strips of wood 3/4" wide and about 7/8" thick, to match the thickness of the shiplap pine decking.  Adding the strips was required since the bottom plate of the wall sat out over the edge of the decking, across the log tongue, and onto this cleat for support. 

Next, we installed the Typar house wrap over the sheathing and stapled it down with a special staple gun that drove the staples through a small plastic disc for increased holding power.  Finally, we installed two wall jacks, one on each side of the wall, with which to lift the wall into place.  I installed some of the foam that we used between the logs on the log tongue beneath the bottom plate, and then two heavy beads of Sikaflex, and we were ready to go.

Once we started lifting, however, it was clear that the wall wasn't lifting right; the left-hand (front) jack was in the wrong place.  To make it right, Bob had to cut out a piece of the sheathing in the center of the gable, and install the jack through the studs there.  So in the pictures, the slot above the window is temporary, and represents where the jack was installed.

Once the jack was repositioned, things went swimmingly, and soon the wall was upright--and looking immense.  We braced it with some metal wall braces, as well as one 2x4, and screwed it to the first floor logs with log screws.  At about this time, it began to rain, thus marking the end of our day, sadly.

The inside of the sheet of OSB at the top right of the window opening is painted green, but this photo makes it look like the hayfield beyond, as the color matches so closely.


With the wall standing, I have the opportunity to help clarify some of yesterday's construction detail.
This is a pocket in the front side of the gable roof.  Later, we'll slide a 4x8 pine beam in here to match the full-length pine rafters that will make up most of the roof framing.  We saw no need to use a real rafter here on the gable end, and Bob came up with this idea.
This is the same thing on the back side of the gable.
This shows most of the shed dormer framing at the gable wall.  The angled framing down the center is the line the roof would take without the dormer (the 12:12 pitch), and is where the shiplap pine overhang boards are nailed.  The portion of these boards that extends outside of the gable represents the plane the roof would take if not for the shed dormer in this area.
The shed dormer roof gets pine rafters too (exposed from inside, as are those in the main roof), but again:  in the gable, we saw no need to use a real rafter, so here is the short piece installed in a pocket similar to those seen a couple photos above.  Unlike conventionally framed homes, the exposed ends of the rafters in this log home will not be plumb cut, but will remain straight cut as seen here.

Now, it's time for a little fun. (Can you tell that it's raining and I have no construction to do?)  I found a picture from exactly one year ago today that happens to be taken at generally the same vantage point from which I take the header (top of page) photos that you see frequently changing.  What a difference a year makes!  In this photo, work on the driveway had just gotten underway--our very first step in the construction process.

The house sits there just as I envisioned it would way back when...even better, perhaps.

The blue arrows are pointing to the same trees in each photo.

June 7, 2005
June 7, 2006

TUESDAY, JUNE 6, 2006


Finally:  a good day!  The day began with fog, but the blue sky was visible through the fog and by mid-morning the fog had cleared, leaving behind bright skies and gentle breezes.  Of course, the forecast was already calling for more rain tomorrow, and the next day, and quite possibly the next day and into the weekend...ho hum.  This winter weather pattern we're in has got to change soon.  It's driving everyone batty.

We got a lot done today, but it was one of those days where much of the progress--important progress--was not something I can show you.  We (meaning mostly Bob) spent a good part of the morning head scratching and figuring out the gable end and the rafter details.  I don't think I can adequately explain the various issues that had to be taken into account when determining the cuts on the rafter ends, all of which needed to be figured before any further building could continue, but suffice it to say that I would have been completely lost without Bob's experience and foresight.  Oh, I would have eventually figured things out, I'm sure, but it would have taken much longer, with more frustration, and probably a less good end result in the end.  And I doubt I would have thought of some of the details he did, meaning that later in the process I would have had to improvise a solution--do-able, but better this way!

I thought it might be interesting, for those of you who have not been to the site, to see a picture showing the relationship between house and barn.


Now, we have a detailed construction manual provided by the log home company, which covers many of the aspects of building the house--particularly those details specific to the logs and some of the related features.  It contains many good drawings of various joints and techniques, but as time goes on we find more and more holes in the coverage.  With Bob's experience, we have never relied entirely on the manual, of course, using it as a guideline to often point us in the right direction; like all writings and other directions, complete reliance on such things can often lead to dead ends.

Log homes are often touted as DIY friendly and capable of being built by a husband-and-wife team.  While this is essentially true, I suppose, it would be extremely challenging for people with little or no building experience and equipment to build one, especially once the house becomes more complicated than a basic cabin or ranch.  The manual is helpful in a general sense, but does not--and cannot, of course--cover every possibility or situation that might arise. 

Why have I gone into this here?  Simply to highlight a frequent conversation that Bob and I have during our building--not as a complaint, but simply an observation.  While the folks at Moose Creek are always available for help by phone or even site visits (if one were to really need assistance), it's clear that people without a fair background in construction might easily run into trouble that would take additional work to get around.  Figuring out the proper way to handle the roof rafters and related areas in our house simply highlighted the potential difficulties that could arise in any construction, and the near impossibility of thinking of everything in advance to avoid problems later.


In any event, after several hours of figuring and making templates, we (Bob) finally had things figured out, and it was time to start building the northern gable wall.  The upstairs walls are traditional stick-framed, while the southern gable wall is solid log.  Both gable ends needed to be built before we could install roof rafters, since the ridge would need the support from the two ends.  To build the north gable, we began by laying out the wall right on the second deck--essentially lofting the wall, to borrow terminology from boatbuilding.  Then, we cut the top and bottom plates, and fitted the studs in between.

One complicated portion of the thought process required to get to this stage was how to handle part of the roof overhang, the portion outside of the rear dormer wall.  (If you can't follow this, you're excused; I had enough trouble envisioning what Bob was suggesting and I was standing right there the whole day.  It took a good bit for me to finally understand the issues.)  Because the side of the rear shed dormer is in the same plane as the gable end, and because we have a "false" rafter on the outside to match the angle of the overhang on the front of the house (rather than have a blank wall run right up to the shallow 5:12 pitch of the shed dormer, the "false", or fly rafter will mimic the 12:12 pitch of the main roof and break up the side for much better appearance), the roof boards, which extend past the roof and into a 12" overhang at the gables, would have to somehow be tacked onto the side of the house in this one area.

I know it's impossible to imagine what I'm talking about, but in any event Bob came up with a very effective way to do this, sandwiching 18" pieces of the WP-11 shiplap pine roof boards (which get installed face down above the rafters, providing the finished interior ceiling just the way they did on the second floor) between the top plate of the angled gable wall and the small dormer wall built directly on top of the rear side of the gable.  Later in the process, we'll hang a fly rafter from these boards to mimic the appearance of the "real" roof, and then add spacers, sheathing, and shingles so that it looks like the remainder of the roof.

By the end of the afternoon, we had the wall built and sheathed and ready to stand up.  Bob didn't have his wall jacks with him, and the wall was too heavy to lift with two people, so we left it right on the deck until the morning.

Next:  the rear dormer wall, and onwards from there.  But given the weather forecast for this week, there may not be a whole lot more to discuss for a few days.


MONDAY, JUNE 5, 2006


Today was "frontier day" on the site.  Bob had some running around to do in the morning, so with his delayed arrival I decided to attack the bark-covered log  for the kitchen post.  Late Sunday, the rain had let up enough to allow me to transport the log down near the shop where I'd have access to water for cleaning and if necessary to loosen the bark, so I was ready to go.

Armed with a draw knife, I began stripping the bark off the log.  I had no idea what to expect; Bob had filled me with debarking horror stories, but I was pleasantly pleased to find that the knife did a great job, and that the bark came off fairly easily.  Nonetheless, I was just as glad that I didn't need to do this to all the logs for the house--it was quite a bit of work, but kind of fun, too.

Once I had the bark removed, I rinsed the log to remove residual dirt and the like from the wood and from the numerous branch ends/knots.  This also loosened up a sort of inner layer of material--a soft, clean white layer of new wood which I then scraped off with the draw knife, exposing the older, straight-grained material beneath.

Later in the day, I used a chisel to knock the knots down flush with the surrounding surface and clean up the surrounding areas a bit.  Then, I used a chainsaw to saw the butt (bottom) end straight and at roughly 90° to the log.  Finally, I cut a notch all the way around the base of the log, extending an inch or so towards the center of the log, to allow the future 3/4" wood flooring in the house to extend beneath the post after installation, thereby avoiding the need to cut and scribe those many pieces of wood.

    


Once I had finished with the log (it only took an hour or so to remove the bark and clean up the log, and it was late in the afternoon before I completed the tasks described above), I moved the chop saw station from the "living room" in the house over beneath the second floor, in the hallway area, to give us room to stage in the living room for the upcoming roof framing work and truss construction.  All the rain from the weekend had left significant amounts of water on the deck and in the basement, so I spent more time pushing the water out with a broom in a generally futile attempt to dry things up; some surprisingly heavy rain showers came through during the morning, something that had not been forecast.  As if we needed the extra water...sigh.

Bob arrived at 1100 or so, and we set to work on the two staircases, a relatively boring task but necessary and useful nonetheless.  We built both sets of stairs--basement and second floor--over a period of a couple hours.


We were expecting a materials delivery today--all the rafters and other roof framing materials. By the time we finished up the stairs, a little before two, the load had not yet arrived, and since we needed those materials to continue, Bob decided to head off to greener pastures.  The delivery arrived around 4, with the truck loaded to the hilt with the 22' rafters (4x8"), ridge (4x12"), and two large piles of the shiplap pine ceiling/roof boards, as well as additional logs for the gable end. 

SUNDAY, JUNE 4, 2006


Rain, rain, rain. 

All I wanted to do this weekend was clean up around the site, move the saw bench under the new ceiling, and work on debarking and cleaning up the raw pine log for the loft support.  But this was not to be:  it rained, often hard, all day Saturday and most of the day Sunday, eliminating all hope of accomplishing even this small list.

That said, I suppose it's better to have the rain come on a weekend rather than during the work week when we really get stuff accomplished.  The forecast is decent for the coming week, so with luck we'll get plenty done.


FRIDAY, JUNE 2, 2006


We began this morning by finishing up the tie plate installation across the various joints between ceiling joists and the log walls and center carrying beam; Bob continued nailing these into place while I undertook the high art of cutting apart wire-collated pneumatic stick nails so that we could hand nail, since we had no dedicated hand nails.  Before long, this work was done.

Next, we needed to build an interior wall--the one defining the north (left-hand) side of the main staircase and the back wall of the closet in Heidi's office, since the ceiling boards needed this wall for support in that area.  As usual, Bob laid out the wall and I cut the studs to length, after which he nailed it together and we raised it into position.  As before, we lagged the wall to the exterior logs with 12" lags through a built-up wall stiffener.

When the wall was complete, I started loading the 7" V-match shiplap pine ceiling boards from the pile in front of the house onto the first floor deck for eventual dispersal.  With exposed ceiling beams, these boards, installed face down, represented the finished ceiling for the first floor.  We had a large pile of random-length boards, from 4' to 16' in length.  I sorted the boards into piles according to length, and then began leaning them up against the second floor framing for easy access from above.

We began at the east (back) wall of the house, and carefully installed the first boards to avoid nailing into the wire grooves routed in the tops of the beams in some areas, ensuring that the pull strings remained free.  While Bob cut and hand-tacked the boards in place from above, I continued sorting and stacking the boards, and also cut apart more of the stick nails for use in the hand nailing.  With 2 or 3 nails per board, the process continued quickly, and before long I stacked most of the boards up on the growing second deck and came up myself to help with the nailing.

We ended up being short by about three boards at the far end of the house, as they had not sent quite enough, so we couldn't completely finish the deck.  More materials were due on Monday, including roof framing and other materials, so I simply ordered a few more of the ceiling boards for the same time.  Once all the boards were in place and tack-nailed, we used the air nailer to shoot 2 nails into each board where they crossed the ceiling joists, permanently securing them tightly in place.

Today was the day that Heidi and I were to close on the sale of the house in North Yarmouth, with a closing scheduled for 4 PM in Yarmouth, so we had to knock off early to allow time to drive down for the closing.  Since we finished up the ceiling boards around 12:30, we decided to call it a day at that point.

Next:  more layout, and preparing for second floor exterior walls, framing, dormers, and roof framing.  That will start Monday.  See you then!

    


THURSDAY, JUNE 1, 2006


This morning, we continued with the ceiling joists, and completed installing the remaining joists by lunchtime.  The installation was straightforward:  cut the 4x8 pine joists to length, and install them in the mortises cut in the 14th log course and the center carrying beam, after applying Sikaflex to the exterior mortise.  The fit was very tight on all the joists, but many of them required significant persuasion from a sledge in order fall into place at the bottoms of the mortises.  But the tight fit meant that the seam where the beams entered the center carrying beam were virtually invisible, which was attractive.

    


After lunch, Bob got to work installing slim metal tie plates where the beams joined the logs and the center beam, to help ensure that they remained tightly in place and held the sides of the house in the proper position, and I began to prepare the applicable joists for wiring, in areas where we planned on lighting in the first floor ceiling.  One thing about log homes:  they force you to plan ahead, and to think several steps ahead at any given time, lest you forget an important step that only has one opportunity to be done. While I had general thoughts of what we wanted,  I had no detailed ideas or plans as to the lighting or other electrical, so at each juncture that these installations were required I was forced to come up with the ideas on the spot, more or less.

We planned to install track lighting in the kitchen, which is located beneath the loft area, and in Heidi's office in the front of the house.  In the first floor bathroom and hallway, we planned a flat ceiling that would hide the pine beams, since the plumbing from the fixtures in the bathroom on the second floor would protrude here anyway and needed to be hidden.  So in these rooms, lighting could be done later in the process.

I wanted to be sure there would be plenty of light in the kitchen, so I figured that I should run wiring down just about every ceiling joist, to allow a multitude of lighting options using track lighting.  With the very real risk of damaging wire run in the tops of the beams with nails used to secure the pine ceiling boards, as well as a layer of Homosote insulation and a final layer of subflooring or final flooring above, Bob and I came up with a plan to use messenger lines instead, with which I would pull the wires in later.

At each location, I used a router with a 3/4" straight bit to plow out a groove in the exterior end of each joist, as close as I could to the wall (until the router base plate hit the log tongue above).  I ran this groove about 16" out from the wall, and about 1" deep.  Then, at the outer end, I drilled from the side of the beam with a 1-1/4" Forstner bit till it mated with the groove within; I did this on both sides of the joists, so that I could run track lighting on either and/or both sides.  To bring the slot a bit further under the eventual second floor framed wall, I drilled another hole at that end, from the top of the log.  With the offset required from the outside of the logs, and a 2x6 exterior wall in these areas, the holes would be well inside the wall framing.  I used a chisel to ease the corners inside, so that it would be easier to pull wires through later.  Finally, I installed a length of poly pull twine as a messenger.  Since I had drilled holes on both sides of the beam, I simply ran the twine around the entire beam, through the holes, and tied it in a knot to hold the inside end in place; later, when entering the wiring phase, I will be able to untie the string and pull wires through the chases.  (I hope!)

As we were proceeding with our respective tasks, the sky darkened to the north and west, and we knew we'd be in for a storm before long.  Preparing ahead, we picked up a lot of the tools that we weren't using and put them away, knowing that when the thunderstorm arrived, it would begin raining hard at once with little warning.  I had just wrapped up the final electrical groove and pull string around 3:00 when it began to rain, signaling the end of our work day.  Later, during the height of what proved to be a severe storm, we watched lightning strike the field nearby--or appear to, at least, accompanied by an immediate and strong clap of thunder.

Next:  another interior wall, a few final details, and the beginnings of installing the ceiling boards.

    

 

Return Home
Photos and Text ©2006-2015 by Timothy C. Lackey.  All Rights Reserved.

 eXTReMe Tracker