Circe | Friday, September 18, 2009

I finished up the sanding, taking care of the toerails and other areas that required hand sanding.  Afterwards, I vacuumed up the dust and solvent-washed the decks to prepare for the next steps.

    
         

         



As always, the high-build highlighted a number of areas containing pinholes and other small voids, so with the decks clean I applied fine fairing compound to fill these holes as needed.  I'd need to do the same process to the hull, but that could wait till later in the process, the next time I had opportunity to move or lower the staging. 

         



During the afternoon, I made some basic measurements so I could begin to prepare a list of materials required for the upcoming interior construction and other woodwork, and began to compile the list for pricing and eventual ordering in the immediate future.
    


Total Time Billed on This Job Today:  5.25 hours